Bluewater Bleo HolmThe Bleo Holm commenced operations in the first half of 1999 at the Ross & Parry Fields for Talisman Energy (UK) Ltd.
Production was suspended in March 2001 to allow onshore topside modifications to the Bleo Holm. These modifications were completed and the vessel returned to the field for offshore hook-up ahead of the project schedule, allowing production to resume on Ross & Parry fields near the end of June and to initiate first oil from the Blake Field just two days later. The Blake field, operated by BG International (NSW) Ltd., is located approximately 10 km from the Ross & Parry fields.